MOTORISTS are being warned of overnight roadworks on the A78 between Wemyss Bay and Inverkip, including two nights when the road will be completely closed.
Surfacing work will take place at Brueacre Junction from Saturday 21 November until Wednesday 2 December, between 8pm and 6am each night, with a variety of traffic management arrangements being used:

— Saturday 21 November to Monday 23 November: rolling two-way temporary traffic lights
— Tuesday 24 November to Thursday 26 November: convoy working from the start of the works to the closure point before the slip roads
— Friday 27 November and Saturday 28 November: full closure of the A78 through Brueacre Junction between the on and off-slips in both directions, with traffic diverted via the slip roads
— Sunday 29 November and Monday 30 November: full closure of the A78 at Brueacre, with a signed diversion in place via Renfrewshire.
— Tuesday 1 December: rolling two-way temporary traffic lights to allow access through the works area in both directions