THE daily closure of the storm-damaged A78 between Skelmorlie and Largs will be lifted from 3pm on Friday.
Contractor Amey, on behalf of Transport Scotland, has confirmed that the road will then be open to all vehicles, in both directions, 24 hours a day, under temporary traffic lights.
The road has operated with a daily closure to through traffic between 9.30am and 3pm since it partially re-opened on 9 November, to give the repair teams an uninterrupted working window to place rock armour along the sea wall damaged by Storm Boelo.

That work is now sufficiently advanced for the remaining repairs to be carried out under a single lane closure without closing the road.
Single lane working will continue under temporary traffic lights while the remaining sea defence, carriageway and finishing works are completed. Road users should still expect some delay at the lights and are asked to allow extra time for their journeys and to drive with care through the works.
Since the road was closed on 25 October, Amey has placed concrete into the voids left beneath the carriageway and installed rock armour to restore the damaged sea defence. The daytime working window has also been used to carry out additional proactive work on other sections of the sea wall along this stretch, strengthening the route against future storms and avoiding the need to return and close the road again later.